The Dunes Wetlands
Location:
Torquay
Project Overview:
Retarding Basin Wetlands
- Bulk earthworks to remove 30,000M3 of clay to provide the foundation of the basin at designed levels.
- Drainage and storm water pit installation around the basin to allow storage and release of water when required.
- Build retaining walls around the perimeter of the basin and landscape.
- Construct Gabions, fencing and landscape elements.
- Construct overflow area designed for a 1 in 100-year storm.
Client:
Land Development Consulting